API 570 Inspection: Gas Systems Boiler Unit H1301 A&B Client: Jordan Phosphate Mines Company (JPMC) For the H1301 A&...
Metal Tie-In Contracts: Bromine Plant Shutdown Client: Seven Mountain Construction (SMC) / Jordan Bromine Company (JBC) ...
NEOM Worker Village: Structural Steel Fabrication Client: Maani Gulf / NEOM As part of the massive infrastructure develo...
Boiler Life Assessment & Integrity Study: Units 1 & 2 Client: AES Jordan PSC For Units 1 & 2 at the AES Jord...
Natural Gas Metering Skid & Pressure Reduction Station Client: Karad System Company End User: Jin Cheng Ceramic Fact...
Nexus and Resource Protection Component 3 – Salt WWTP Client: Arab Towers Contracting Co. (ATCCO) In the development of ...
Bi-directional Flow Train A&B Shutdown Client: Egypt Gas Co. Methods: RT, PT, UT, UTT, PAUT, MT During this critical...
Harp Replacement Project: HRSG #1 & #2 Client: AES Jordan PSC Methods: PT, MT, UTT, UT, RT, VT, WQT, WPS For the Har...
JGPT Capacity Enhancement: Arab Gas Pipeline Client: Egypt Gas Co. Methods: RT, PT, UT, MT, VT As part of the strategic ...
NEOM Coast Guard Building Client: Al Fahd Company Trading, Industries and Contracting For the NEOM Coast Guard facility,...
New 16” Pipeline to RH-67 (Wellhead) Client: National Petroleum Company (NPC) Methods: RT Synergy managed the quality va...
Supply Compressed Gas Station with Natural Gas Client: Egypt Gas Co. Methods: RT For the infrastructure connecting a hig...
Odorization Unit & PE Pipeline: Quwairah Industrial City Client: Egypt Gas Co. Methods: RT, PT, MT For the Quwairah ...
Construction of new soda tanks , (P33-A), (P33-B). National Chlorine Industries During the expansion of the National Chl...
RTG Cranes Structural Repair & Supervision Client: Aqaba Container Terminal (ACT) At the Aqaba Container Terminal, R...
NEOM O3 Oxagon Project: Structural Steel & Hanger Fabrication Client: Al Fahd Company Trading, Industries and Contra...
Annual Ammonia Tank Maintenance Client: Nabil Food Industries Methods: MT, UTT, VT Synergy conducted the annual safety a...
Fabrication & Welding: Auxiliary Boiler Stack Part A & B Client: Bitar Metal Industries & Marine Service Co....
Fourth Unit Shutdown: Risha Station Client: Samra Electric Power Co. (SEPCO) Methods: UT, PT (Fluorescent & Visible)...
RH 53 Pipeline Construction (10 km) Client: National Petroleum Company (NPC) For the RH 53 Pipeline project, Synergy was...
Quwairah Industrial Area: Reduction & Metering Station Client: Egypt Gas Co. / Ministry of Energy Methods: RT, PT, M...
New AMONIA PIPELINE Extension JORDAN DISTRICT COMPANY “JDE” Ammonia transport requires the highest tier of safety due to...
Sulphuric Acid Tank T5501-A: Major Overhaul Client: Jordan Phosphate Mines Company (JPMC) The storage of sulphuric acid ...
Amra & Jerash Rigs: Body Repair & Structural Validation Client: National Petroleum Company (NPC) For the Amra an...
New Piping System Inspection at JOTC Client: Issa Haddadin & Partners Co. / Jordan Oil Terminals Company (JOTC) As p...
Boiler Piping System Repair Client: Jordan District Energy Co. (JDE) For this critical district cooling and heating infr...